Brownouts, ancillary services and transmission charge

* This is my article in BusinessWorld last February 23, 2017.

bw

Rotational and scheduled brownouts for several hours about once a month, then unscheduled short brownouts from time to time, have become a regular experience in the two provinces of Negros island. Despite the installation of many huge solar plants in recent years.

I am currently in Sagay hospital in Negros Occidental to visit my seriously sick father. Last night, there was brownout for about 10 minutes, the hospital’s generator set immediately takes over to supply electricity to their patients and staff.

The Facebook page of the Central Negros Electric Cooperative (CENECO) gives frequent advisory of power interruption that lasts for nine hours (8 a.m. to 5 p.m.) until this month.

Stories and testimonies of frequent brownouts in many cities and municipalities of Negros Oriental in 2016 are also reported in dumagueteinfo.com.

In June 2016, the Department of Energy (DoE) said that line congestion is building up in Negros Occidental due to many solar power plants operating in the province. The abrupt influx of solar power plants is causing the main line, transmission and interconnection lines to congest (Sun Star Bacolod, June 10, 2016).

This month, Negros Occidental Electric Cooperative (NOCECO) explained that one of the main reasons of higher electricity is the increase in the transmission charge from P1.0538/kWh in January 2017 to P1.1777/kWh in February 2017 or an increase of 0.1239/kWh. The transmission rate hike is due to the increase in the ancillary service charges of the National Grid Corporation of the Philippines (NGCP).

There are at least two issues here. First is the presence of more brownouts in Negros island despite its having the most number of installed solar power plants per sq. km. of land in the whole country, more than 300 MW.

Solar power is very unstable and intermittent, zero output at night and very low output when it is cloudy, or power fluctuates wildly if clouds come and go in minutes. So there should be more ancillary services or standby power plants, usually natural gas or diesel plants, that should quickly provide power when thick clouds come and when evening comes. Still, this causes power fluctuations that damage machines, engines and appliances running on electricity and the leadership of Negros chamber of commerce and industry have pointed this out to the DoE and NGCP last year.

Second, how is the NGCP regulated and accounted in its transmission charge pricing and assets management?

Power generation is deregulated and hence, the extent of competition among many players is the main regulator of the generation charge. Distribution charge is regulated by the Energy Regulatory Commission (ERC) because distribution utilities (DUs) like Meralco and the roughly 119 electric cooperatives (ECs) nationwide are all monopolies in their respective franchise areas.

So while there are 120+ distribution monopolies composed of private DUs and ECs, the NGCP is a single, national monopoly in power transmission.

There are 12 different charges in our monthly electricity bill. The top six in the table below, and these five charges with lesser rates: (7) universal charge, (8) cross subsidy charge, (9) lifeline rate subsidy, (10) senior citizen subsidy, and (11) feed in tariff allowance (FiT-All). No. (12) are value-added tax (VAT) and other government taxes, these are huge too but not included in the table because they are unrelated to the electricity system.

Of these 12 different charges, subsidies and taxes, the smallest is #10 while the fastest growing is #11, FiT-All: P0.04/kWh in 2015, 0.124/kWh in 2016, and set to rise to P0.23-P0.25/kWh this 2017, the ERC still has to decide on the Transco petition for FiT-All hike (see table).

20170222cf205
Notice in the table above the following: (1) In 2013 vs. 2017, all five charges have declined in rates in 2017 except transmission charge which has remained practically the same at P0.91/kWh. And (2) In 2014 vs. 2015, a similar pattern where all five charges have declined in rates in 2015 except transmission charge which has even increased to nearly P1/kWh.

The possible explanations why the transmission charge by NGCP seems to be the odd man out among the top six charges are (1) rising cost of more ancillary services as more intermittent solar-wind power are added into the grid, (2) it passes its own system loss to the transmission charge, (3) it simply behaves like a typical monopoly, revenue-maximizing as consumers and other players have zero option of other service supplier/s.

20170222be0f6Brownouts and expensive electricity, these are ironic events in our modern world. We should have stable and cheap electricity, no brownouts even for one minute except after heavy storms and typhoons that knock down electrical posts and power lines.

Government should step back in some heavy regulations like forcing intermittent solar-wind into the grid which can discourage some developers who can build stable and cheaper power like coal and natgas plants. And giving high price guaranty for 20 years to renewables like wind-solar is wrong and punishing the consumers. Technology changes very fast, the costs of solar and wind equipment are falling fast, so why lock the high price for 20 years? This is wrong.

Advertisements

The PEMC-NGCP Electricity Summit 2016, low ESSPs last October, high FIT-All next year

The annual Electricity Summit jointly organized by the Philippine Electricity Market Corporation (PEMC) and the National Grid Corporation of the Philippines (NGCP) will be held next week in Davao City, the home of President Duterte. PEMC is the market operator, the Wholesale Electricity Spot Market (WESM) while NGCP is the system operator.

I attended theElectricity Summit 2015 held at the Crowne Plaza in Ortigas. Compared to most conferences that I attend, it was an odd or weird one. The organizers and speakers are the energy regulators (DOE, ERC), market operator and system operator, and the audience are the regulated market players. So during the open forum, I think the audience were  hesitant to ask critical questions and comments to the guys who regulate them and operate the system for them. I think I stood 2 or 3 times to ask questions because the huge conference hall has a generally friendly atmosphere to the organizers.

The program this year is a bit different mainly because (1) EPDP is involved, an independent institute, (2) there are speakers from the WB and ADB, and (3) the President is a keynote speaker. Last year, among the key speakers were from (1) the ASEAN Power Grid, (2) the International Energy Agency (IEA), and (3) Mr. MacDonald, the Australian consultant who justified the PEMC structure of many government representatives in the board and still call it an “independent” agency. Provisional program of Summit 2016 as of November 17.

el-summit

I have heard the presentations by Majah, Laarni and Geoffrey at the recent PH Economic Society (PES) conference last November 8. The WB and ADB guys will likely be talking about “more renewables please to save the planet” and indirectly say “we offer pretty climate and energy loans to save the planet.” 🙂

What will be new there will be the proposed electricity market and transmission connection for Mindanao. Will the session also tackle the privatization of huge hydro power plants in Mindanao, the Agus-Pulangi plants, others? I doubt it. These plants are still under another government corporation, the Power Sector Assets and Liabilities Management Corp. (PSALM).

Registration is P15,000 per head, not cheap. People from Metro Manila, Visayas must also fly to Davao and get a hotel room for a night or two.

Meanwhile, PEMC sent me their latest press release with a good news: the Effective Settlement Spot Prices (ESSPs) in WESM further fell from PhP2.86/kWH in September to PhP2.48/kWH in October 2016 billing period. Good news, indeed. ESSPs are average prices paid by wholesale customers for energy purchased from WESM. Meralco has been getting more of their power supply from WESM over the past two or three months, something like 15-20% of their power supply. Mura eh, good decision.

Supply – demand dynamics. Higher supply, more competition among gencos, lower prices. Limited supply while demand remains high, higher prices.

This is the power generation mix for October 2016 in the Luzon-Visayas grids, PEMC data. Will the planet saviours who keep insisting on “more wind-solar please to save the planet” be happy with frequent, long hours of blackouts daily, more candles and noisy gensets 365 days a year? Solar + wind can only supply 2.3% of the total electricity need in Luzon-Visayas grids including Metro Manila.

el-summit2

Meanwhile, PEMC will not report that there is a bad news to low ESSPs — that the FIT-All (feed in tariff allowance) will naturally rise big time next year.

FIT-All = (Total FIT collections by the renewables firms) – (collections from WESM)

So, since the collections from WESM are low because of low ESSPs while the total FIT collections will be high as more solar-wind are added to the grid with their expensive guaranteed price (for 20 years, mind you), FIT-All will naturally rise. From 4 centavos/kWh in 2015 to 12.40 centavos/kWh this year, to about 20 centavos/kWh in 2017?

If we combine these: (a) FIT under-recoveries in 2015 because of the low FIT-All of 4 centavos + (b) FIT under-recoveries in 2016 because of low ESSPs and insufficient 12.40 centavos + (c) more expensive solar-wind power added to the grid, the resulting FIT-All by 2017 will be high.

The FIT administrator is another government firm that owns the country’s grid system and assets, the National Transmission Corporation (Transco). I do not know yet how much Transco has petitioned the ERC for the FIT-All next year.

Again, my bottomline: government interventions in setting the energy mix, in setting fixed and guaranteed pricing for the variable renewables (solar, wind, biomass, run-of-river or small hydro), in granting mandatory dispatch for these renewables, are all wrong. They can lead to more expensive electricity, more unstable supply and “brownouts-friendly” electricity